Difficulty

Because of the ACI’s all-encompassing scope, the team faced a wide array of challenges. Some are the obvious technical issues: for example, getting a new portal to integrate seamlessly with the existing systems. Some were less obvious, less technical, but no less daunting. For example, how does one dispose of the packing material that came with over 3,400 laptops? In general, the difficulties fell into three categories: Preparing the backend network; managing delivery logistics; and training users and gaining their acceptance.

St. John’s foresaw the need to upgrade its backbone network to improve performance, reliability and manageability. Working with strategic partners Cisco and BearingPoint (with Contemporary Computer Services Inc. managing the physical details), St. John’s installed a completely new network, upgrading the campus to gigabit switched Ethernet. The backbone network is now fast enough to handle the additional load of a wireless network add-on. The network is standards based, so there is no concern that wireless access points would not be able to interact with the backbone network. Finally, the network is physically distributed but centrally manageable, so wireless nodes can be added where needed but configuration can be managed from the central command center. Additional domain controllers, software update and virus scanning servers were installed to handle the anticipated load of more than 12,000 new computers over four years.

The logistics of distributing over 3,400 laptops were very complex, especially when the immovable deadline for distribution was less than five months from project approval. Deliveries were tracked closely to ensure that laptops would arrive when staff was assembled to prepare them. Mountains of packing materials had to be removed. Millions of dollars of equipment needed to be inventoried and secured. An auditable process was designed and documented to ensure up to 200 students per hour could receive a laptop, peripherals and training. Fifty staff members were trained on various aspects of preparing and distributing laptops.

It was clear that training and education would be key to user acceptance. Separate education tracks were designed for students and faculty members. Students received an hour-long orientation session before the laptops arrived, and then participated in Public Safety and "care and feeding" sessions on distribution day. In addition, every student received handouts and the laptops were equipped with an on-board help system.

The team anticipated some difficulty with faculty acceptance and integration of the ACI into their existing curriculum due to the short time period. Thus, daylong Faculty Institutes that focused on techniques for incorporating technology into pedagogy as well as on the mechanical aspects of using the laptops were scheduled. However, the team initially anticipated a modest response and planned only a few of these sessions during the summer of 2003. Instead, over two-thirds of the full-time faculty requested laptops and training over the summer; more than tripling the need for the Faculty Institute sessions. James Pellow, Executive Vice President and Treasurer, notes, "One of the most impressive things to see was how the faculty accepted the ACI. We thought it would be difficult training and encouraging faculty to introduce the technology into the classrooms in such an aggressive timeframe. Through very strong leadership and the sheer excitement, we found that faculty overwhelmingly embraced the program. They lined up in numbers."

In addition to the challenges above, the team was hit by a significant setback when the Northeast suffered a multi-day power outage just three days before distribution began. Because the entire distribution process was automated and depended on network access to the St. John’s student records database, the team had to restore the University back-end network while distribution preparations continued. All of this was achieved while phone, cell and e-mail networks across the region remained unavailable.